Sequence decides whether a large project is financed. Youngsik Ahn, Director, Head of Export and Agency Finance, Sub-Saharan Africa, Citi, made that point in Session 03, Energy, Power, Infrastructure and Industrial Corridors, at the 16th UK–Africa Investment Summit in London on Friday 11 September 2026. The moderator, Eric Olanya, Country Director, Gridworks Development Partners, asked what lies behind Citi’s record on projects in Uganda with UK Export Finance and other export credit agencies.

Youngsik Ahn at the 16th UK–Africa Investment Summit, London.
Youngsik Ahn at the 16th UK–Africa Investment Summit, London.
Watch the UKAIS 2026 recording. Source: UK–Africa Investment Summit on YouTube.

Citi’s footprint in Uganda

Mr Ahn said Citi operates in 35 countries in sub-Saharan Africa, with a local presence in 15, including Uganda. The bank works closely with the Government of Uganda. He said it has arranged large infrastructure financings for sovereign borrowers, including road, agriculture and hospital projects.

Teamwork across the whole chain

The most important factor, he said, is teamwork. A large project needs the line ministry, the Ministry of Finance, a reliable contractor and exporters to work together. It also needs an export credit agency such as UK Export Finance. No bank delivers such a project alone. It takes collaboration, partnership and trust among all parties.

“This type of project absolutely requires teamwork.” Youngsik Ahn, Director, Head of Export and Agency Finance, Sub-Saharan Africa, Citi #WMUTENZA

The official report sets out who must move together. They are the line ministry and Ministry of Finance, sponsors and contractors, exporters, and banks with export credit agencies. A project that government treats as a priority is not automatically financeable. It must show a credible route to construction, operation and repayment.

How a contractor should approach the bank

Mr Olanya asked how a contractor should approach Citi for a project built and financed under an export credit structure. Mr Ahn said the bank is open to exploring such projects alongside export credit agencies. Its first step is to understand how developed the project is and how much export content it carries.

The earlier Citi engages with the contractor and understands the project and its foreign content, the greater the chance of delivering a financing structure for the contractor and the government. Mr Olanya summed up the advice. The earlier sponsors involve the banks, the more likely they are to secure finance.

Youngsik Ahn at the Summit on Friday 11 September 2026.
Youngsik Ahn at the Summit on Friday 11 September 2026.

Why timing shapes the structure

The report records the contrast directly. Early engagement means lenders join during development. Late engagement means lenders arrive after terms are set. Its key takeaway is that the earlier banks and export credit agencies are engaged, the greater the likelihood of a commercially workable financing structure.

Eligibility for export credit support depends on sovereign credit quality, exporter participation, project structure, transaction size and repayment capacity. UK Export Finance reported approximately £1 billion in remaining financing capacity for Uganda. That capacity is available to projects that are prepared, not to concepts.

What investors should do next

Contractors and sponsors should treat the first meeting with the bank as part of project design and not as a request for finance at the end.

Government officials can help by naming a single focal point who can convene the ministries, the contractor and the lenders. Sponsors can send a brief to the Summit team.

Register your interest in UKAIS 2027

The 17th UK–Africa Investment Summit takes place on Friday 10 September 2027 in London, UK (Venue TBC). A 12-Month Delivery Scorecard will report progress on the actions agreed in 2026.

Register your interest in UKAIS 2027

References

Post-Summit Summary (PDF) Official Post-Summit Report (PDF)

Willy Mutenza | Chairman, UK–Africa Investment Summit